Mise à jour groupée des échantillons
Date: 15 Avril 2024 Ressources Blencowe Plc
("Blencowe" ou la "Entreprise")
Bulk Sample Processing underway at Pilot Plant Facility in China
Progression towards Product Qualification and Offtake Contracts
Blencowe Resources Plc (LSE: BRES) is pleased to report significant progress on the Definitive Feasibility Study ("DFS") works for the 100%-owned Orom-Cross graphite project in Uganda including commencement of the 600 tonne bulk sample test work at the Jilin Huiyang New Material Technology Company Ltd ("Jiliin") facility in China.
Points forts:
· Traitement des échantillons en vrac - commencement of the 600-tonne commercial scale processing at Jilin in China marks a significant step forward for Orom-Cross DFS.
· Off-take Agreements Progress - senior management and potential offtake partners to meet during April 2024 to advance off-take discussions following strong interest in the large-scale test work, samples delivered to date, and Orom-Cross products across the board.
· Final Sample Delivery - both 96% concentrate and 99.95% spheronised purified graphite ("SPG") provided from this latest bulk sample testing are expected to be delivered in Q2 2024 to potential off-taker parties in sufficient quantity for review, leading to product qualification and ultimately contracts.
Following the delivery of the 600 tonne bulk sample materials to China, processing has commenced at the Jilin facility. This same facility effectué précédemment successful bulk metallurgical test work for Blencowe on the 100-tonne Orom-Cross sample in 2023.
Blencowe plans to utilise this product to generate large volumes of both 96% concentrate and 99.95% uncoated SPG product for final qualification with potential off-take partners. This process aims to maintain the same consistently high quality as previously delivered via this commercial-scale production process in 2023.
Senior management will visit both China and South Korea over the next few weeks to continue discussions on offtake agreements. Strong interest has been shown to date and Blencowe is confident that this will continue with the ongoing large-scale test work.
Cameron Pearce, président exécutif a commenté;
"This latest 600 tonne bulk sample testing is a critical part of our DFS. We aim to demonstrate that end products maintain the same high quality and purity in commercial scale processing that have already been achieved in all previous testing to date. The 100 tonne testing last year confirmed this quality maintains to scale and we are confident we can achieve similar results from this latest 600 tonne testing. Thereafter we will have sufficient quantity of 99.95% SPG to provide for testing with tier one offtakers for product qualification."
M. Pearce a ajouté "We are making significant progress across all DFS objectives. Orom-Cross is a world class graphite project with unique characteristics, and son potentiel is becoming increasingly evident as we deliver each milestone."
Pour de plus amples informations s'il vous plaît contacter:
Ressources Blencowe Plc Sam Quinn |
www.blencoweresourcesplc.com Téléphone : +44 (0) 1624 681 250
|
Relations investisseurs Sasha Séthi | Tel: + 44 (0) 7891 677 441
|
Financière Tavira Jonathan Evans | Téléphone : +44 (0) 20 3192 1733
|
Twitter https://twitter.com/BlencoweRes
LinkedIn https://www.linkedin.com/company/72382491/admin/
Contexte
Projet de graphite Orom-Cross
Orom-Cross est un projet de graphite potentiel de classe mondiale à la fois par la taille et la qualité du produit final, avec une composante élevée de flocons grossiers plus précieux dans le gisement.
Un permis d'exploitation minière d'une durée de 21 ans pour le projet a été délivré par le gouvernement ougandais en 2019 à la suite de travaux historiques approfondis sur le gisement. Blencowe a achevé avec succès une étude de préfaisabilité sur le projet en juillet 2022 et est maintenant dans la phase d'étude de faisabilité définitive alors qu'il se dirige vers la première production.
Orom-Cross se présente comme un vaste gisement à ciel ouvert peu profond, avec une ressource minérale indiquée et présumée initiale JORC de 24.5 Mt à 6.0 % TGC (teneur totale en graphite). Cette ressource a été définie à partir de seulement environ 2 % de la superficie totale des immeubles, ce qui présente un potentiel de hausse considérable. Le développement de la ressource devrait bénéficier d'un faible taux d'exploitation et d'opérations de creusement gratuites ainsi que d'une énergie hydroélectrique abondante et peu coûteuse provenant du réseau national, garantissant ainsi de faibles coûts d'exploitation. Avec toutes les infrastructures majeures disponibles sur le site ou à proximité, les coûts d'investissement seront également relativement faibles par rapport à la plupart des pairs du graphite.
RNS peut utiliser votre adresse IP pour confirmer le respect des termes et conditions, pour analyser votre interaction avec les informations contenues dans cette communication et pour partager cette analyse de manière anonyme avec d'autres dans le cadre de nos services commerciaux. Pour plus d'informations sur la manière dont RNS et la Bourse de Londres utilisent les données personnelles que vous nous fournissez, veuillez consulter notre Politique de confidentialité.